August 2002--Under the terms of the Wendell H. Ford Aviation
Investment & Reform Act (AIR-21), the Federal Aviation Administration
(FAA) has awarded design grant funds to Akron Airport to implement
safety related improvements. These design improvements include
a parallel taxiway to the recently constructed runway, a lighted
helipad, a paved crosswind runway, and improvements to the airport
access road, detailed below.
The parallel taxiway to Runway
7-25 will allow aircraft to exit the main runway after use, which
improves capacity, making the airport safer.
The helipad will improve emergency
access and separate the ROTOR and fixed wing air traffic, making
the airport safer.
The crosswind runway (Runway 11-29)
is also a safety improvement outlined in the Airport Master Plan.
Runway 11-29 is currently used when winds are out of the northwest.
The availability of a paved secondary runway improves the safety
of aircraft operations in crosswind conditions.
Funding is also approved for design
and reconstruction to widen the existing access road into the
Airport (John Street Extension) from 20 feet to 24 feet, including
associated drainage and safety improvements. The improved road
and drainage system will improve Airport access for customers
and emergency vehicles.
These projects comply with the
improvements outlined in the Airport Master Plan Update completed
in 2000. This planning document was developed through input from
the Town of Newstead, Village of Akron, airport owners, and nearby
residents to improve the airport and meet current FAA safety and
capacity related standards.
Christian Airmen will continue
to work with both the Village of Akron and the Town of Newstead
to improve the airport. It is anticipated that construction will
commence in spring of 2003.